Texas has restarted environmental permit reviews for data centers. Georgia has set separate billing terms for the biggest power users.
The race for land and electricity to run AI data centers got a new push in Texas. State environmental regulators have resumed reviewing data center permits, ending a pause ordered by Gov. Greg Abbott, the Texas Tribune reported on Nov. 17.
The Texas Commission on Environmental Quality (TCEQ), which handles air-pollution and construction stormwater permits, said it got notice from Abbott’s office that the state grid operator, ERCOT, had finished gathering information on data centers’ potential community impacts. “The agency has resumed its normal permit review process and will evaluate applications under all applicable state and federal laws and regulations,” TCEQ spokesperson Laura Lopez said.
ERCOT was tracking about 474 gigawatts of large-load requests in June, roughly 90% of them data centers, according to ERCOT figures reported by Latitude Media. Approvals to connect new data centers to the grid were still paused as of Latitude Media’s Nov. 16 report, while ERCOT’s audit finishes. The grid operator plans to file its findings Dec. 10. Developers are now rushing to secure Texas data center permits, the Financial Times reported, as summarized by Tom’s Hardware.
Why the clock matters
Governor-elect Gina Hinojosa, who defeated Abbott on Nov. 3, said during the campaign that she would keep data center approvals paused until legislators pass new state laws, according to the Tribune. She takes office in January. That gives developers a window.
How the pause unfolded:
- August: Abbott asked ERCOT and electricity regulators to audit data centers seeking grid connections and paused approval of those interconnections.
- Sept. 21: He asked TCEQ to pause data-center-related environmental permits until ERCOT finished its review.
- October: After advocacy groups found some permits still being cleared, TCEQ suspended them and shut down its automated filing system, the Tribune reported.
- Nov. 5: ERCOT told regulators it had received responses from 93% of 465 projects surveyed. It plans to present full findings to the Public Utility Commission on Dec. 10.
Not everyone accepts the restart. Public Citizen, an advocacy group, said TCEQ began issuing permits without sharing ERCOT’s results with communities and called on commissioners to resign. Opposition had grown across the state from residents of both parties worried about the grid, pollution and water, the Tribune reported.
Georgia’s different deal
Georgia has taken another route. Its regulators say the goal is to let the projects come while keeping their costs off other customers.
In January 2025, the Georgia Public Service Commission unanimously approved a rule allowing Georgia Power to bill any new customer using more than 100 megawatts under separate terms. The rule allows contracts of up to 15 years instead of five, plus minimum billing requirements, so a data center can’t leave before paying for infrastructure built for it, according to the PSC. Every such contract must go to the PSC for review.
Critics say the rules leave Georgia Power wide discretion. Former PSC member Bobby Baker called them “essentially worthless” in 2025, The Current reported, and the Southern Environmental Law Center says they remain insufficient. Georgia Power told lawmakers at the time that residential customers “will pay nothing” for the 3,300 megawatts it was then planning for.
“We want to keep Georgia the best place to do business, but data centers will need to bear the cost of their electricity acquisition,” PSC Vice Chairman Tim Echols said at the time.
The PSC has kept building on that rule, according to its September 2026 fact sheet:
- In December 2025 it certified 9,985 megawatts of new generation, about 80% of it expected to serve data centers. The PSC says Georgia Power has now secured customers for all of it.
- Base rates are frozen through 2028.
- Georgia Power agreed to cover those costs through 2031 if data center contracts fall short.
- Under an August 2026 agreement tied to a 3,200-megawatt contract, Georgia Power said it would not seek to recover a departing data center’s costs from homes and small businesses, and it raised its promised downward pressure on the typical residential bill to at least $15 a month for 2029 through 2031.
What it means for land, power and your money
- Power is the new zoning. In both states, where a data center can plug in decides where it gets built. That can make access to substations and transmission lines a factor in land near these projects.
- Watch the dates. In Texas, ERCOT’s Dec. 10 report and January’s change in governor could reshape the rules. Anyone with land or projects near proposed sites can follow the PUC docket.
- Read your utility’s fine print. Georgia’s regulators say their rules are meant to keep data center costs off household bills. Ask your utility, in any state, how large new customers are charged.
- Local opposition is real. Community buy-in can affect project timelines.
This article is for educational purposes only and is not investment or real estate advice.